West Texas Runtime Guarantee Calculator Natural Gas Compression

Contracts & Credits · Haynesville Shale

Haynesville:
the fleet average said no credit was owed. 4 units disagreed.

Illustrative scenario. The company and figures are fictional. The math is the same the free tools use.

Cypress Bayou Energy rents 12 compressors in DeSoto Parish under a 98% runtime guarantee. Every month the vendor's invoice includes a one-line summary: fleet runtime, guarantee met, no credit due. In June it said 98.4%.

The production engineer had a nagging feeling about four of the units. So she checked them one at a time.

Same hours, two answers

At 98% over 30 days, each unit may be down 14.4 hours before a credit is owed. Across the whole fleet that is 172.8 hours, and the fleet was down 138. Averaged, the guarantee was met.

Unit by unit, it was not:

Credit owed, unit by unit$3824 of 12 units broke the guarantee See the math
A fleet average finds$0the healthy units hid the bad ones See the math
Worst unitH-0531 hours down, 16.6 beyond its allowance
Show the mathHide the mathHow each figure above is worked out, step by step.
Credit owed, unit by unit$382
  1. Hours in the month30 days × 24 h720 h
  2. Down hours allowed per unit720 h × (100% − 98%)14.4 h
  3. H-01(26 h − 14.4 h) × $6,800 ÷ 720 h$110
  4. H-03(22 h − 14.4 h) × $6,800 ÷ 720 h$72
  5. H-05(31 h − 14.4 h) × $6,800 ÷ 720 h$157
  6. H-07(19 h − 14.4 h) × $6,800 ÷ 720 h$43
  7. 8 units stayed inside the allowancedown no more than 14.4 h, so no credit$0
  8. Credit owed, unit by unit$110 + $72 + $157 + $43$382
A fleet average finds$0
  1. Hours in the month30 days × 24 h720 h
  2. Down hours allowed per unit720 h × (100% − 98%)14.4 h
  3. Down hours, all unitsevery unit’s down hours, added up138 h
  4. Fleet allowance14.4 h × 12 units172.8 h
  5. Average rent per unitevery unit’s rent, added up, ÷ 12 units$6,800.00
  6. A fleet average finds(138 h − 172.8 h) × $6,800.00 ÷ 720 h$0
orange scenario numbergray result of an earlier stepSteps are rounded for display; totals use the exact numbers.Same formulas as the Runtime Guarantee Credit Calculator

Read your contract for one word

Most rental contracts measure the guarantee per unit. Some measure it per fleet. The difference decides whether eight healthy units can quietly cover for four bad ones. If yours says per unit and the invoice reports a fleet average, the invoice is answering a different question than your contract asks.

The credit is the small part. $382 will not change anyone's quarter. 40.4 hours of excess downtime on 4 units, at Haynesville gas rates, is what actually cost money, and it is the same four units every month until someone names them.

What Cypress Bayou does now

  • Runs the credit unit by unit every month, from their own callout times
  • Sends the vendor the unit list with the invoice dispute, not a fleet number
  • Tracks H-01, H-03, H-05 and H-07 as a watch list
Run these numbers yourselfOpens the Runtime Guarantee Credit Calculator with this scenario filled in. Change anything to match yours.
Guarantee
98%
Days in the month
30 days
Units
12 rows
Check Your Units in the Credit Calculator